Who enforces fire pump testing: Houston or Harris County?
Fire pumps are usually found in mid-rise and high-rise buildings, large warehouses and campuses, and the local rules depend on the AHJ. Inside the City of Houston, the Houston Fire Department's Fire Marshal's Office applies LSB Standard No. 02, which sets the weekly and annual pump tests below. In unincorporated Harris County, home to many distribution centers along the Beltway and the Grand Parkway, the Harris County Fire Marshal's Office (HCFMO) enforces the Harris County Fire Code. HCFMO's FAQ says to search the address in the Harris County address search; "sheriff" in the Law Juris column means unincorporated Harris County. Other metro cities have their own fire marshal.
In HCFMO's jurisdiction, every service provider who inspects or tests fire protection systems must register with The Compliance Engine and submit all test, inspection and service reports there, on the schedule in the adopted fire code. The contractor files and pays the filing fee, not the owner. Fire pumps are listed as their own system in HCFMO's tracking, alongside sprinklers, standpipes and private hydrants.
How often a fire pump must be tested in Houston
The weekly runs may be done by authorized building or contract personnel under the manufacturer's guidelines and NFPA 25. Keep the written log; LSB 02 requires records for at least three years (§2.3.5).
- Diesel engine pumps: weekly operating test without water flowing, started automatically, running at least 30 minutes, logged in writing (LSB 02 §2.5.5.1).
- Electric motor pumps: weekly operating test without water flowing, started automatically, running at least 10 minutes, logged in writing (LSB 02 §2.5.5.2).
- All fire pumps: annual flow test at pressure recording churn, rated flow and 150 percent of rated flow, by an approved service company, with a service tag (LSB 02 §2.5.5.3).
- Emergency power: if the pump is on a generator, the annual generator load test checks fire pump starting loads (LSB 02 §2.4.3.2).
Texas license required for fire pump testing
Under the State Fire Marshal's sprinkler rules, a sprinkler system includes its water supply, such as a fire pump, and testing means periodic checks of water-based fire protection systems, expressly including fire pump tests (28 TAC §34.706). That puts the annual pump test within sprinkler licensing.
Hire a company with a TDI/SFMO Sprinkler Certificate of Registration (SCR-General), with the test performed and the tag signed by an RME-General or RME-General Inspector licensee. Repairs to the driver, controller or transfer switch may need other trades, such as a licensed electrician or the engine dealer, working with the sprinkler company.
Weekly pump runs: what building staff record
LSB 02 lets authorized building or contract personnel do the weekly no-flow run, as long as the pump starts automatically, runs for the full time (30 minutes for diesel, 10 for electric), and the test is written down. A useful log entry has the date, who ran it, how it started, run time, suction and discharge pressure, and anything unusual such as alarms, leaks, overheating or a pump that did not start on its own. Diesel logs should also note fuel level and battery condition.
Hand the log to the contractor before the annual flow test. Trends in the weekly readings help the technician spot a problem that a single annual test can miss.
Coordinating annual tests on the same water supply
The fire pump, the sprinkler system, the fire line backflow assembly, standpipes and private hydrants all share the same water supply, and several of their annual and five-year tests flow water or take part of the system out of service. Scheduling them together, and with the generator load test if the pump is on emergency power, means one coordinated impairment and one set of notices instead of several.
Before the flow test, confirm with the contractor where the water will be discharged, whether a test header or flow meter is installed, and how long the system will be impaired. In unincorporated Harris County, make sure the contractor files the pump report through The Compliance Engine.
What the annual fire pump flow test covers
The contractor should give you a test report with readings, not just a tag. It should show:
- Suction and discharge pressure and flow at churn (no flow), at 100 percent of rated flow and at 150 percent of rated flow.
- Speed (rpm), and for electric pumps voltage and amperage on each phase at each flow point.
- A comparison against the pump nameplate and the original acceptance test or manufacturer's curve.
- Controller, automatic start and alarm functions, including power transfer if the pump has an alternate source.
- Packing, bearings, coupling and, for diesel, engine fluids, batteries and fuel level.
- Any pump that does not meet nameplate data reported to property management and the owner, as LSB 02 §2.5.5.3 requires.
What a failed pump test or tag means
If the pump or another part of the sprinkler system is out of compliance but not an emergency impairment, the contractor attaches a yellow tag and notifies you and the AHJ in writing within five business days (28 TAC §34.721). If the system is out of order, for example the pump will not start or the water supply is interrupted, that is an emergency impairment: a red tag, immediate oral notice and written notice within 24 hours (28 TAC §34.722).
Inside Houston, a required fire protection system placed out of service for emergency or unscheduled repair requires an immediate call to HFD Office of Emergency Communications at 713-884-3143, and another call when it is restored. Planned, lengthy outages need written notice to the fire code official at least 7 business days ahead (LSB 02 §2.3.6).
What affects the cost of fire pump testing
FireMarket does not publish prices. Bids depend on:
- Pump size and driver type (electric or diesel), and whether there is a jockey pump and transfer switch.
- Whether a test header is installed, or flow must be discharged through hydrants or hose, and where the water can go.
- Flow meter versus hose-and-pitot testing.
- Coordination with the generator load test, sprinkler inspection and backflow test.
- Corrective work found during the test, which should be quoted separately.